HVAC Conversion Seth North Residence Hall (CSUS 2020)
(Estimated Project Cost: $2,150,000)

Project Description
This project provides for the conversion of HVAC systems in Seth North Hall. The existing heating units will be replaced with HVAC units that are thermostatically controlled within each room.
Time-Line
| Design |
in progress
|
Bid Opening
|
Winter 2012
|
Contract Award
|
Spring 2012
|
Start of Construction
|
Spring 2012
|
Completion of Construction
|
Summer 2013
|
| Occupancy |
Summer 2013
|
Project Administered by: CCSU
Project Status Report
Funding for this project received in Summer 2011. Construction of this project will take place over two summers.