Stadium Seating & Associated Support Facilities Phase IV Athletic Fields (CCSU Funds)
(Estimated Project Cost: $3,335,000)

Rendering may not reflect the final construction.
Project Description
The Arute Field Stadium, which is used for recreation, lacrosse and football, currently has grandstands on the home side of the field but no seating on the visitor’s side. This project proposes to install aluminum bleachers and support facilities on the visitor’s side of Arute Stadium. This bleacher system will accommodate up to 2,400 spectators. The proposed support facility will house men’s and women’s restrooms and storage facilities that will serve all of the athletic and recreational fields in this area.
Time-Line
| Design |
Complete
|
Bid Opening
|
Complete
|
Contract Award
|
Complete
|
Start of Construction
|
Complete
|
Completion of Construction
|
Fall 2011
|
| Occupancy |
Fall 2011
|
Project Administered by: Department of Construction Services
Project Status Report
Anticipate that this project will be complete in December 2011. Certificate of Occupancy should be attainable by Fall 2011. The contract award for this project was delayed six months by the Department of Construction.