Soccer Field: Phase V (CCSU Funds)
(Estimated Project Cost: $1,890,000)

Rendering may not reflect the final construction.
Project Description
This project calls for the installation of a new synthetic turf field between Arute Field and other recreation/ball fields. The new surface will allow for additional utilization throughout the day and evening due to its durability and the field will be equipped with lighting that supports the opportunity for evening recreation activities.
Time-Line
| Design |
Complete
|
Bid Opening
|
Complete
|
Contract Award
|
Complete
|
Start of Construction
|
Complete
|
Completion of Construction
|
Fall 2012
|
| Occupancy |
Fall 2012
|
Project Administered by: CCSU
Project Status Report
Project is currently under construction. The soccer project requires a bleacher seating system to complete this project. The surface was completed in Spring 2011 and is currently being utilized. The bleacher seating will be completed in coordination with Track (Phase VI).