East Campus Environmental Impact Evaluation and Infrastructure Design
(General Obligation Bond Funds)
(Estimated Project Cost: $1,800,000)

Rendering may not reflect the final construction.
Project Description
This project calls for an environmental impact evaluation study of property located on the east side of route 9 across from the main campus. The study is required before any planned facilities can be constructed on the site. This project also includes the design of approximately 5,280 feet of roadway, sidewalks and underground utilities.
Time-Line
| Design |
Project Delayed- Bond Funds not available
|
Bid Opening
|
Contract Award
|
Start of Construction
|
Completion of Construction
|
| Occupancy |
Project Administered by: Department of Construction Services
Project Status Report
Awaiting funding approval by the State Bond Commission.