Davidson Hall Window Replacement Phase II (CSUS 2020)

(Estimated Project Cost: $950,000)

 


 

Project Description

Phase I of this project, which was completed in February 2010, provided for the replacement of 172 windows located within the first and second floors of the main building. Phase II will provide for the replacement of up to an additional fifty-seven (57) windows, sidelights and window assemblies in the south wing and the areas on each side of Founders Hall. Restoration work will include the removal and replacement of existing window sashes, screens, deteriorated frames, and hardware.

Time-Line

Design Complete
Bid Opening
Fall 2011
Contract Award
Winter 2012
Start of Construction
Spring 2012
Completion of Construction
Fall 2012
Occupancy N/A

 






Project Administered by: CCSU

Project Status Report

Additional funding received in Spring 2011.