Objective 7.1
|
|
Increase the square footage of academic space for classrooms, laboratories, faculty offices, library and research, and student support.
|
| |
Reference to Previous Strategic Plans: ASP 04. 5.1 FSP 99. 1.1, 3.5
|
ExCom Member:
|
CAO
|
Assessment Tool:
|
Space Inventory
|
Baseline:
|
913,160 GSF (2007-2008)
|
Goal:
|
1,160,225 GSF
|
Progress:
|
914,190 GSF (2009-10)
|
|
|
|
|
Enabling Activities:
|
- New Classroom/Office Building totaling 75,055 (GSF). CSU received legislative approval for selection of Architect/Engineering consultant and is awaiting contract approval. Construction is estimated to take three years from completion of design and bond approval.
- Engineering Lab totaling 5,000 sq. ft. CCSU funding has been received project is in design phase. Will be constructed in 2010-11.
- Library addition totaling 161,980 GSF.
|
|
BACK TO GOALS & OBJECTIVES